| Severn
estuary outer tidal reef proposal (early version)
Up-to-date website with pdf downloads: Severn
Tidal Reef Project
A tidal barrage for the Severn Estuary designed from an environmental
perspective.
Author: Rupert Armstrong Evans, Armstrong Evans & Associates
* June 2008
Background
| Tidal Reef System | Engineering
Issues | Environmental Issues
| Economic Issues | Summary
of all Issues
BACKGROUND
TO THIS PROPOSAL
The debate as to whether to build a barrage
across the Severn Estuary to generate electricity has gone
on for well over 100 years and has once again come to the
fore with the Government announcement of proposals to build
additional nuclear plants and/or the promotion of 'green generation'
including from tidal power. But within the environmental lobby
a major split has opened up between the promoters of a 'Big
Barrage' (the Severn Tidal Power Group) on the one hand, and
the wildlife interests (WWF, RSPB, FOE and local councils)
on the other. Fear of increased flood risks, damage to wildlife
habitats and compromised navigation are but some of the many
and complex issues.
In this proposal I am presenting
a radically different concept for tidal power generation that
is driven by the need to address environmental issues before
rather than after the project has been formulated. Most of
the studies into tidal generation have been approached from
the perspective of known hydraulic and civil engineering practices.
I am suggesting that a consensus of 'environmental imperatives'
are used to define these requirements, in much the same way
as the 'North Sea' defined the requirements for building oil
platforms, and not the other way around. I suggest that it
is the requirements of the large low-head water turbine manufacturers
that have defined the previous proposals, and many of the
resulting problems are then being addressed as mitigation
measures.
 |
This proposal is for a
barrage 'system' and is not at this stage tied to one
particular turbine design or barrage location, though
initial investigations point strongly towards an 'Outer
Barrage' between Minehead and Aberthaw, with bidirectional
generation. I am seeking a reasonable compromise between
the environmental constraints and a technological solution
that some turbine manufacturers might wish to avoid because
it opens up the market to many more engineering competitors,
with a consequential lowering of the potential profit
margins. |
The 'Big Barrage' between
Cardiff and Weston (Brean and Lavernock), is designed to provide
the necessary hydraulic head for conventional low-head water
turbines, and this involves delaying the tides by many hours
to produce this head difference. It is this long delay in
the tidal cycle that causes most of the potential problems.
Massive disruption to the levels and flow patterns within
the estuary will result from the high localised discharges
from the 40MW turbines. The impacts of such disruption are
many, complex and may be very detrimental to the environment
as well as navigation. The S.T.P.G barrage comprises a lot
of 'hard engineering structures' in the form of powerhouses,
sluices and ( ship locks which will have a significant visual
impact. It is also designed with an adequate freeboard to
protect the powerhouse and roadway from flooding and damage.
Such a structure is very expensive on account of the head
differential and wave action that it is required to withstand
and the quantity of material requires for its construction
is very large.
THE SEVERN
TIDAL REEF SYSTEM
This new system offers a radically different
approach to other proposed systems because it is based on
a much more modest soft-engineered structure. It is intended
to be almost totally environmentally benign and to take account
of the ecological constraints from the outset. The impounding
structure is much smaller than a conventional barrage but
it still has the potential to generate as much electricity
as a full height barrage. It will require significantly smaller
quantities of material during its construction, so the cost
and environmental impacts on land or through dredging operations
will also be much reduced.
 |
The 'Tidal Reef'
would typically be comprised of 20 km of turbine caissons
located astride a seabed causeway of pre-cast concrete
foundation units anchored with piles and 'armour stone'.
Over 1000 turbines of around 10 metres diameter would
produce 5000MW, but for about twice the generation period
of the proposed Cardiff-Weston barrage. The annual generation
could therefore be in the order of 20 TWh because the
area enclosed by the 'Reef is so much greater than for
the Cardiff-Weston barrage.
The operation of the reef/barrage
requires only a modest alteration to the tidal cycle
amounting to a delay of around two hours as opposed
to six hours for the large barrages. The key to this
design is that it uses a large number of simple fixed
flow turbines that work on a very low constant head
difference across the structure. Floating caissons would
contain the turbines or a movable 'crest gate' reaching
to the surface of the water would divert the flow into
fixed caissons sitting on the foundation 'causeway'.
This arrangement allows the structure to 'track the
changing tide level' and maintain the small head difference
irrespective of the stage of the tide so that the turbines
that are operating run at near constant power and efficiency.
|
The electricity generation
can therefore spread over a longer period and the turbines
and civil structures do not have to be designed for high intermittent
stresses caused by using higher heads. It is a much more modest
structure which is also less intrusive and damaging to the
environment. Water turbines for very low heads are large,
but need not be expensive, as the materials required for their
construction can be significantly cheaper than the single
regulated Kaplan turbines proposed for the other barrage projects.
The arguments in favour of
this proposal are outlined in this proposal, but if any of
the many arguments are substantiated, there is in my opinion,
a godd case for this proposal to be considered in much more
detail to bring it into a similar frame of reference as the
other competing proposals, particularly as the environmental
impact of the other proposals is causing great concern.
ENGINEERING
ISSUES
A barrage located much further West near
Minehead would offer, according to the Black & Veatch
study of 2007, around 20Twh/annum of generation, which is
about 50% higher electricity production than the proposed
Cardiff-Weston barrage. The lower mean tidal range at this
location of around 9 metres, as opposed to 11 metres at Cardiff,
should not in itself be a disadvantage with the proposed 'Reef
system.

Location of proposed tidal
reef, compared with barrage |
The longer generation
period would make it easier to synchronise
the generation period with periods of peak demand. Furthermore,
a relatively small increase of head of around half a
metre over the nominal operating head of 2 metres, will
enable the scheme to operate at an overload capacity
to meet peaks for short periods without causing a significant
increase environmental problems.
The greater storage capacity offered
by the outer barrage location further enhances this
feature of the project because the percentage change
in water level/tidal phase is much less significant
and within the range variations that vou would exoect
from factors such wind direction. |
The cost to build the grid connections
will be considerable but for the Somerset end of a reef barrage
near Minehead there is an advantage in being much closer to
the existing Hinkley Point 400 KV grid lines than for a barrage
at the Cardiff-Weston site.
The core of the reef system
is a simple causeway structure that is low enough so that
it can be overtopped by storm surges and exposed at low tides
without sustaining damage. Pre-cast cellular foundation modules
could be placed with land based tracked cranes or gantries
being much easier and cheaper to operate than crane barges
and jack-up platforms.
 |
The turbine modules
would be installed along pre-cast foundation modules
using the foundation causeway for access, which would
considerably increase the 'operating window' when compared
to marine access that is severely limited by the state
of the tide and prevailing weather conditions.
Crest gates incorporated into the
structure would prevent the tidal flow from passing
over the turbine modules if they were sitting on the
foundation causeway. If the turbine modules are buoyant,
they could be installed so that could move up and down
over the causeway foundation. It will be more economic
to build than a conventional barrage that is designed
to counter the waves and support a higher differential
pressure of at least 8 metres.
The reef is almost entirely made up of turbine
modules, which are comprised largely of water
passages and voids, so in addition to the low aspect
ratio of a caisson when compared to an embankment, much
less material required. The height of the barrage is
also reduced by not having to protect a roadway, having
to counter storm surge levels or to take the higher
operating head necessary for the 'big barrage's Kaplan
turbines. |
Over 10 million tons of rock fill
would be saved by not having to dredge a new shipping channel
and further dredging would be saved by not having a relatively
small number of very large turbine caissons that need a greater
installation depth. The Southern landfall is adjacent to the
Somerset Steam Railway which is experiencing severe coastal
erosion problems and has been used to transport armour stone
from a nearby quarry, for this and the recent Minehead sea
defence work.
Much of the construction
can be achieved using land based construction machinery such
as tracked cranes, as opposed to floating crane barges that
are considerably more expensive to operate. By providing a
series of intermediate 'island refuges' it will not be necessary
to remove construction equipment to the shore at high tide.
The construction period for the large
barrage is estimated at 15 years, whereas Mulberry
Harbour the pre-fabricated floating dock built for the D-day
landing in Normandy took only six months to build in secret
around the UK before being installed in Normandy under enemy
fire. It comprised 9km of cast concrete caissons, not dissimilar
to my current proposal. A time scale of 15 years before revenue
earning would make the big project uneconomic from the start.
Revenue earning could start
within a couple of years of work commencing on the 'Reef Project'
and well before the barrage is completed. This is possible
because of the low differential head. So although the water
will tend to flow around the completed sections, generation
should be possible at reduced efficiency. A total construction
period of five or six years would make the project much more
attractive financially.
 |
Navigation requires a
depth of over 20 metres to accommodate the existing generation
of cargo ships. The Cardiff-Weston project incorporates
a new dredged shipping channel to Avonmouth requiring
the removal of around 10 million cubic metres of material
and a ship lock capable of passing the largest ships at
all stages of the tide. A prime consideration for the
existing and planned ports, is maintaining the high water
levels. With the 'Reef Project' there is a small head
differential across the barrage and near high water when
the head is no longer adequate for power generation, the
whole barrage is opened to allow the remaining water to
continue up the estuary. The reduction in the peak tide
level would thus the minimal but in the event of a storm
surge the maximum levels could be controlled by delaying
the opening of the barrage. |
Energy lost before high water
can in part be recaptured by allowing generation to start
earlier on the falling tide. Ships could pass through the
barrage unhindered during a period of about two hours before
high and low water. A single 'flash gate' could be used at
any stage of the tide up to the capability of a particular
ship and depending on whether it was passing with or against
the tide. A 'raceway' or very low lift ship loch for two metres
of differential head would also be required for smaller and
less powerful vessels, as opposed to 10 metres of differential
head for the 'big barrage' scheme. The low lift lock could
be a completely pre-cast structure that is floated into place
like a floating dry dock.
Land drainage outfalls at
a number of locations are compromised by the Cardiff-Weston
barrage 'holding' the high water for several hours in order
to obtain the necessary operating head for the turbines. The
'Reef Project' requires only a short delay, which could be
as little as one hour, to allow a fall of around 1500mm before
generation can start.
Large Kaplan turbines of high
specific speed have good full flow efficiency at rated head
and R.P.M. but these ideal conditions are only met twice in
every tidal cycle, so all other stages of the tide are a compromise,
giving lower efficiency and output. By contrast the 'reef
system uses many smaller turbines, that will have slightly
lower full flow efficiency but which run under 'ideal design
conditions' for almost the whole of the operating period.
The water turbines used in a barrage such as the Ranee scheme,
are usually unidirectional, so a significant portion of the
civil engineering cost is associated with sluices and by-pass
channels to let the tide in. Bi-directional turbines, whilst
requiring a more ingenious hydraulic design, save on these
associated structures such as sluices.
Simple fixed-flow turbines
can be built by many more sub-contractors around the country,
so the price per kW will probably be the same or even lower
than the large turbines that can only be built by a handful
of international companies. The use of smaller and more innovative
turbine designs is possible because of the modular design
and more companies have the physical capability to build them.
By limiting the operating head of the turbines to less than
two metres, the differential pressure exerted on the structure
in much lower than for a barrage, making the construction
easier and less sophisticated so pre-cast unanchored concrete
caissons similar to those used in the construction of Mulberry
Harbour for the D-day landing, would allow the construction
to proceed rapidly during the 'windows of opportunity' when
the tides and weather are favourable.
Significant engineering design challenges
will need to be addressed; these include the size, number,
type and layout of the turbines, the effect and method of
controlling marine growth, the systems for installing and
maintaining the turbine modules and the behaviour of the caissons
under storm conditions.
The routing of service and power cabling
through the foundation causeway to the islands and the flexible
umbilical connections will all need development, but much
of the technology already exists and is used in the offshore
oil industry.
The modelling of the flows through such a structure, how it
impacts on tide levels, estua-rine currents and potential
generation and operation, will be the first step in examining
the merits of this proposal.
The number of man-hours required
for offshore operations will have to be kept to a minimum
if the cost are to be contained, reducing the risks of engineering
failures and environmental disturbance if the concept is kept
simple and the turbine modules are relatively small, though
numerous.
ENVIRONMENTAL
ISSUES
The 'Reef System' is designed with the environmental
constraints such as Natura 2000 to the fore, as opposed to
mitigation measures after the engineering has been designed.
The phase change in the tides and the alteration of the natural
regime will be significantly less than for a conventional
barrage, resulting in minimal disruption to migrating fish,
bird life and the mudfiat ecology. The 'Reef is in effect
one continuous line of small turbines, typically 3MW each,
so the tidal flow is not diverted across to a smaller number
of large turbines of over 30 MW each that would radically
alter the water flow patterns within the estuary, with the
possible consequences of erosion or silting.
Migratory fish can pass safely
through the 'Reef by incorporating slower running, low specific
speed turbines of fixed geometry. This type of turbine need
not be more expensive to build on account of the simplicity
of design, the lighter construction and the use of lower cost
materials, all made possible because the operating head is
both low and constant. For fish to pass through the turbines
without injury it is necessary to have wide clearances, smooth
surface finishes and the lack of pinch points. A differential
operating head of around two metres will not adversely affect
fish by rupturing their swim bladders, which might occur if
the head difference was greater. The choice of low specific
speed turbines with a small number of blades with wide openings
is feasible on this very low head, which should allow the
safe passage of salmon and sea mammals.
Loss or altered habitat resulting
from the altered tidal range is largely avoided with the 'Reef
System' simply because the working head is so much less and
the resulting changes very much smaller. Flooding and peak
tides should be reduced upstream of the reef and only marginally
altered on the seaward side because the delay in the tide
cycle is so short. Difficulties with land drainage outfalls
should also be reduced, simply because the deviation from
the natural tidal range will fall within what is experienced
naturally, even if the pattern is altered marginally.
Dredging and quarrying will
be much reduced with the 'Reef Project' when compared to the
18 million mt" required for the big barrage. On-shore
infrastructure environmental impact will be lower for the
'Reef because the more constant generation will make better
use of the electrical infrastructure and 'hard engineering'
structures will be physically smaller. Distributing the construction
of caissons between several shipyards around the country will
cause less disruption to the sensitive local environment and
possibly improve employment in locations that do not have
the capability to build the large 'big barrage' caissons'.
The aesthetics of the estuary
and surrounding landscape, while being altered, will not be
altered as much as that required by a 'big barrage'. The 'Reef
will be almost totally submerged at most stages of the tide,
while the 'big barrage' will tower ten or fifteen metres above
low water level, and four or five above average high water
levels.

ECONOMIC
ISSUES
The material required for construction the
'Reef Project' will be significantly less than that required
for a 'big barrage' because it is lower and only has to withstand
two metres of head difference, and there is no need to have
expensive 'non-revenue generating' technology such as sluice
gates. No road is incorporated, because the cost of providing
the extra height and protection from waves is not the most
economic way of providing a road crossing. For each metre
increase in height you have to provide about five metres of
width. So a structure half the height of the 'big barrage'
uses about a quarter of the material. No conventional ship
lock would be needed as a single or double gate flush lock
will allow ships to pass through at any stage of the tide,
and dredging a new shipping channel would also be avoided.
The generation profile of
the 'Reef Scheme' would be flatter, generating less power
but for a longer period. This requires smaller generator and
electrical transmission capacity, and a corresponding reduction
in the intrusion on the landscape as well as improved electrical
efficiency and utilization. Returns from the electricity generated
will be seen well before completion of the project using the
'Reef System' improving the early economic returns significantly.
The simple fixed-flow turbines
for a 'Reef System' can be built by many more subcontractors
around the country allowing local manufacture, so the price
per kW will probably be the same or even lower than the large
turbines that can only be built by a handful of international
companies. For maintenance the complete sealed turbine units
could be lifted out and replaced with a serviced unit. Unlike
the 'big barrage' turbines that are far too heavy to lift
out once installed and require conventional dry powerhouses
with personnel inside them to be protected from the elements.
A mixed public/private partnership
would be much easier to implement with the 'Reef, because
the main infrastructure including the underwater foundations
could be public funded, with secondary power developers bidding
for space to install a range of competing turbine devices
along the barrage (similar to the planned 'Wave Power Hub'
off the North Cornwall coast)
The Risks during installation
of a 'Reef are reduced because the technology is kept simple
and 'mammoth' operations are kept to a minimum or eliminated
all together. Because of the nature of the working environment
with strong tides and poor weather, the installation of the
huge caissons for the 'big barrage' would be very risky. Building
the scheme in smaller steps reduces risk. The long-term performance
of the project will be more secure if several technologies
and competing developers install many turbines. The chances
of catastrophic failure are much reduced with the 'Reef Concept'.
The Unknowns relate mainly to the environmental impacts and
large scale marine operations, such as placing the caissons.
The smaller the barrage and alteration of the tidal regime
the lower the environmental risks and the cost of mitigation
measures. The smaller the caissons are, the less the risk
there is of an expensive accident.
SUMMARY:
The engineering issues
This proposal addresses the hydraulic engineering concepts
that are necessary to meet the perceived and stated environmental
concerns that are known to the author. It does not set out
to define locations, technologies or operating systems but
to present a logical direction in which the desien process
can move while taking into account a wide spectrum of environmental
concerns.
Limiting the operating head
of the turbines to less than two metres, the differential
pressure exerted on the structure in much lower than for a
conventional big barrage'. The construction is then easier,
less sophisticated and cheaper. The construction can also
proceed more quickly during the 'windows of opportunity' when
the tides and weather are favourable.
Navigation requires a depth
of over 20 metres to accommodate the existing generation of
cargo ships. Dredging operations would be far more modest
for the 'Reef System' as ships could pass through a single
'flush lock gate' or a ship lock for only two metres of differential
head as opposed to 10 metres of differential head for the
'big barrage' scheme.
Large Kaplan turbines of
high specific speed have good full flow efficiency at rated
head and R.P.M. By contrast the 'reef system uses many smaller
turbines that will have slightly lower full flow efficiency
but which run under 'ideal design conditions' for almost the
whole of the operating period.
The environmental issues
The 'Reef System' is designed with the environmental
constraints such as Natura 2000 to the fore, and is in effect
one continuous line of small turbines, typically 3MW each,
so the tidal flow is not diverted across to a smaller number
of large turbines of over 30 MW each that would radically
alter the water flow patterns within the estuary, with the
possible consequences of erosion or silting.
Migratory fish can pass safely
through the 'Reef by incorporating slower running, low specific
speed turbines of fixed geometry. A differential operating
head of around two metres will not adversely affect fish by
rupturing their swim bladders or injure sea mammals.
Loss or altered habitat resulting
from the altered tidal range is largely avoided with the 'Reef
System' simply because the working head is so much less and
the resulting changes very much smaller. Flooding and difficulties
with land drainage outfalls should also be reduced.
Dredging and quarrying will
be much reduced with the 'Reef Project', on-shore infrastructure
will be less and distributed construction of caissons will
cause less disruption to the sensitive local environment.
The aesthetics of the estuary
and surrounding landscape, while being altered, will not be
altered as much as that required by a 'big barrage'.
The economic issues
The material required for construction the
'Reef Project' will be significantly less than that required
for a 'big barrage' because it is lower and only has to withstand
two metres of head difference, no road is incorporated, no
conventional ship lock would be needed, and dredging a new
shipping channel would also be avoided.
The generation profile of
the 'Reef Scheme' would be flatter, generating less power
but for a longer period. Returns from the electricity generated
will be seen well before completion of the project using the
'Reef System' improving the early economic returns significantly.
The simple fixed-flow turbines
for a 'Reef System' can be built by many more subcontractors
around the country allowing local manufacture, so the price
per kW will probably be the same or even lower than the large
turbines that can only be built by a handful of international
companies.
A public/private partnership
is well suited to build the 'Reef Project'. The main infrastructure
including the underwater foundations would be public owned
and power developers would finance and build the turbine systems.
The Risks during installation
of a 'Reef are reduced because the technology is kept simple
and 'mammoth' operations are kept to a minimum. The long-term
performance of the project will be more secure if there are
several technologies and competing developers.
Version 2.1 (25th June 2008)
later
pdf version
Rupert Armstrong Evans
Armstrong Evans & Associates
www.evans-engineering.co.uk
Go to top |